在波斯灣Pars油田南部第22-24期的24B平臺作業中,Petro Gohar Farasahel Kish Co.?(PGFK)完成了8口井的鉆井工作。據總經理Masood Ziari介紹,這項工作耗時20個月,平均每71.8天打一口井,在今年年初,PGFK完成了24A平臺的鉆井工作。在第22、23和24期,開發了22和23兩個主要平臺以及24A和24B兩個輔助平臺。PGFK共鉆探38口井,這項作業每天可增加Pars油田南部天然氣產量10億立方英尺,所有平臺預計在明年十月投產。
來自/Offshore 10月31日消息 ? ? ? ? ? ? ? 編譯/尉晶
TEHRAN, Iran?–?Petro Gohar Farasahel Kish Co.?(PGFK) has completed drilling of eight wells from platform 24B for phases 22-24 of the?South Pars field?in the Persian Gulf.Drilling took less than 20 months to complete, according to managing director Masood Ziari, and on average 71.8 days per well. Earlier this year PGFK completed drilling from platform 24A.Records established at 24B included drilling a 32-in. section in nine hours. Some of the wells featured a 60° angle.Phases 22, 23, and 24 are being developed via two main platforms (22 and 23) and two satellite platforms (24A and 24B). PGFK is drilling a total of 38 wells. The campaign will add 1 bcf/d gas to production capacity at South Pars.?All platforms are expected to be operational by October 2017.
石油圈原創 www.h29736.cn
未經允許,不得轉載本站任何文章:
-
- 尉 晶
-
石油圈認證作者
- 本科畢業于西安石油大學地質學專業,現就讀于中國石油大學(北京)地質工程專業。對于油氣行業發展動態、實時資訊有著全面的了解,致力于將最專業、最地道的業內發展近況傳播給每位讀者。