中國石化新聞網訊 據路透社5月15日倫敦報道,雪佛龍公司的一名發言人周一表示,雪佛龍公司日前關閉了其在澳大利亞的巨大高更液化天然氣(LNG)出口廠的第一條LNG生產線。為了更換一個已損壞的裝置,第一條LNG生產線的停產將持續一個月。 雪佛龍公司在一份聲明中說,高更LNG出口廠的第一條LNG生產線是在5月12日一個流量計量裝置發生故障以后停止生產的。 在去年3月以后發生了一連串意外關閉以后,雪佛龍公司一直在努力保持這個投資540億美元項目的穩定生產。 雪佛龍公司高更LNG出口廠的第3條生產線在今年3月份投產,使得該廠LNG年總出口能力提高到了1560萬噸。 李峻 編譯自 路透社 原文如下: Chevron Shuts First Gorgon LNG Export Plant Unit For Around A Month Chevron Corp has shut the first production line at its giant Gorgon liquefied natural gas (LNG) export plant in Australia and expects the outage to last about a month in order to replace a faulty device, a spokesman said on Monday. “Production on Gorgon Train 1 was stopped on May 12 due to a failure of a flow measurement device,” the company said in a statement. Chevron has struggled to maintain stable production at the $54 billion project, which came on stream in March last year, following a string of unplanned shutdowns since then. Gorgon’s third production line started up in March 2017, bringing combined export capacity to 15.6 million tonnes.