據《油氣雜志》7月31日墨爾本報道,雪佛龍澳大利亞分公司31日宣布,其在西澳大利亞州的價值340億美元的惠特斯通液化天然氣(LNG)項目的首條生產線目前正處于試運行的最后階段。LNG生產應該在今后的幾周內開始。 這個項目原本計劃在去年年底之前投產,后來推遲到今年年中,然后再推遲到今年8月份投產。與雪佛龍澳大利亞分公司規模更大的Gorgon-Jansz項目所記錄的170億美元超支相比,惠特斯通LNG項目超支50億美元算是適度超支。 雪佛龍澳大利亞分公司上游部門負責人杰伊·約翰遜日前在美國的第二季度簡報會上表示:“惠特斯通LNG項目的海上平臺和管道已啟動并運行,而生產井的初始產能令人鼓舞?!?李峻 編譯自 油氣雜志 原文如下: Wheatstone LNG to come on stream in August Chevron Australia reports that the first production train of its $34-billion Wheatstone LNG project in Western Australia is now in the final stages of commissioning. Production should begin in the next few weeks.
The project was originally slated for an end-2016 on-stream date, later amended to mid-2017 and then again to August 2017. Cost overrun, $5 billion, is modest compared with the $17-billion overrun recorded for the company’s larger Gorgon-Jansz project. Head of the company’s upstream division, Jay Johnson, said in a quarterly briefing in the US that the Wheatstone offshore platform and pipeline to shore were up and running and initial performance of the production wells has been encouraging. ?