為能源工業提供設備建造、工程設計和承包服務的Lamprell公司宣布:該公司本應于2016年第二季度交付的一座自升式鉆井平臺將延期交付。
公司周二稱:該平臺目前進入試運行的最后階段,已進行了一系列設備測試以備交付。Lamprell沒有透露該平臺及買方的名稱。在最后測試階段,由一家原始設備制造商提供的設備出現了技術問題,從而導致交付延期。
調整后的交付日期定在八月中旬。此次交付延期意味著公司需要對該項目合同進行修訂,并支付一定的違約賠償金。但Lamprell公司董事會稱,修訂合同的成本和可能蒙受的大部分損失將由原始設備制造商承擔。
除了該平臺待交付以外,Lamprell還有其它六座平臺正如期建造。放眼全球,市場行情不容樂觀,此次交付延期將在一定程度上影響Lamprell公司2017年的收益。
來自/Offshore Energy Today 7月26日消息 ?編譯/趙美園石油圈原創www.h29736.cn
Lamprell, a provider of fabrication, engineering and contracting services to the energy industry, has informed that delivery of the jack-up drilling rig which had been scheduled for delivery in 2Q 2016 has been delayed.
The company said on Tuesday that the rig is in its final stages of commissioning and has undergone a series of equipment proving tests in anticipation of delivery to the client. Lamprell did not reveal the name of the rig nor its client. During this final testing, a technical issue has arisen with equipment supplied by an original equipment manufacturer (OEM) and this has resulted in a delay to the delivery of the rig.
The revised date for delivery of the rig is now expected to be mid-August. The resultant delay in the delivery means that the Group could be exposed to contractual remedies on the project including liquidated damages. However, Lamprell said that the board anticipates that the majority of the remedial costs and potential damages exposure as a result of this delay will be recoverable from the OEM.
Apart from the delivery of this rig, all other six rigs that Lamprell are currently constructing remain on schedule. More broadly, the market environment remains very challenging and this will impact the company’s revenues in 2017, Lamprell said.